The expected activity time in PERT analysis is calculated as:
A) the simple average of the optimistic, pessimistic, and most likely times.
B) the weighted average of a, m, and b, with m weighted 4 times as heavily as a and b.
C) the sum of the optimistic, pessimistic, and most likely times.
D) the sum of the optimistic, pessimistic, and most likely times, divided by six.
E) the sum of the activity variances, divided by six.
Correct Answer:
Verified
Q77: A network consists of the following list.
Q78: A network consists of the activities in
Q79: Which of the following statements concerning CPM
Q80: The PERT pessimistic time estimate is an
Q81: The beta distribution is used in project
Q83: Analysis of a PERT problem shows the
Q84: A project being analyzed by PERT has
Q85: A contractor's project being analyzed by PERT
Q86: Which of the following statements regarding PERT
Q87: A project being analyzed by PERT has
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents