Two activities on different critical paths that share no common nodes are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, the manager should crash activity(ies) ________, adding ________ to project cost.
A) B; $2,000
B) C; $2,000
C) C; $1,000
D) B & C; $3,000
E) B & C; $4,000
Correct Answer:
Verified
Q121: Pirmin's Bike Shop is behind on a
Q122: Which of the following is NOT a
Q123: Three critical path activities are candidates for
Q124: Given the critical path below, calculate the
Q125: A network has been crashed to the
Q126: Three critical path activities from the same
Q127: Identify several advantages of using PERT (and
Q128: Which of the following is NOT performed
Q129: _ is decreasing activity time in a
Q130: If an activity whose normal duration is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents