Question 41
Multiple Choice
When it is necessary to reduce project duration and resources are constrained, which of the following is NOT a reasonable option?
Question 42
Multiple Choice
When reducing project duration, the duration for a project that is optimal is at the point where
Question 43
Multiple Choice
When determining which activity to crash, there are other factors that should be assessed beyond cost. Which of the following is NOT one of these factors?
Question 44
Multiple Choice
Which of the following is NOT one of the more commonly used options for cutting project costs?
Question 45
Multiple Choice
Which of the following is NOT a technique for accelerating project completion when resources are not constrained?
Question 46
Multiple Choice
Which of the following correctly calculates an activity's cost slope?
Question 47
Multiple Choice
The relationship between the normal point and the crash point is assumed to be
Question 48
Multiple Choice
Sometimes very high __________ costs are recognized before a project begins and reducing these costs through shorter project durations becomes a high priority.
Question 49
Multiple Choice
Which of the following projects would be least benefited if additional resources were added?
Question 50
Multiple Choice
When a project manager must reduce project duration but resources are constrained, creating a software program that will have less functionality than originally planned or building a house without the bonus room and the basement that the owner originally specified in the plans would both be examples of
Question 51
Multiple Choice
Which of the following is NOT a rational reason to reduce project duration?
Question 52
Multiple Choice
Reducing project duration
Question 53
Multiple Choice
In selecting the best activity to crash you would first select the activity with the
Question 54
Multiple Choice
One way of reducing project costs is identifying tasks that _________ can do themselves.
Question 55
Multiple Choice
All of the following are disadvantages of scheduling overtime EXCEPT
Question 56
Multiple Choice
When reducing project duration, the crash cost per unit has to be calculated and the maximum units each activity can be reduced must be known. After this, the critical path must be identified. What is the next step?