There are four resources and four jobs to be done. Assume there must be one-to-one matching between jobs and resources. The time required for each resource to do each job is as follows:
What is the optimal assignment of resources to jobs?
A) 1 to A; 2 to C; 3 to B; 4 to D
B) 1 to B; 2 to D; 3 to C; 4 to A
C) 1 to C; 2 to B; 3 to A; 4 to D
D) 1 to D; 2 to B; 3 to C; 4 to A
E) 1 to A; 2 to C; 3 to D; 4 to B
Correct Answer:
Verified
Q62: One disadvantage of appointment systems is
A)Capacity can
Q63: The owner/operator of the local franchise of
Q64: In an assignment model where there are
Q65: There are four resources and four jobs
Q66: The president of a consulting firm wants
Q68: The president of a consulting firm wants
Q69: The owner/operator of the local franchise of
Q70: Scheduling in service systems may involve scheduling:
(I)the
Q71: What is the optimum job sequence for
Q72: There are four resources and four jobs
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents