Question 1
Multiple Choice
Which of the following statements, about the test reporting activities for a project adopting an iterative lifecycle model with very short iterations (e.g. two weeks iterations) , is correct? Number of correct responses: 1
Question 2
Multiple Choice
Which of the following statements describing the consequences of specifying test conditions at a detailed level is NOT true? Number of correct responses: 1
Question 3
Multiple Choice
The main objectives the senior management team wants to achieve are: - to reduce the costs associated with dynamic testing - to use reviews to ensure that the project is on course for success and following the plan - to use reviews as a well-documented and effective bug-removal activity following a formal process with well-defined roles - to determine the effectiveness of reviews in terms of phase containment - to improve phase containment effectiveness Which of the following answers would you expect to describe the best way to achieve these objectives? Number of correct responses: 1
Question 4
Multiple Choice
Consider an agile team adopting Extreme Programming (XP) with five developers and one tester without any coding experience. To which of the following activities would you expect the tester will contribute most? Number of correct responses: 1
Question 5
Multiple Choice
For which of the following activities would the costs be classified as a cost of detection? Number of correct responses: 1
Question 6
Multiple Choice
After the presentation, you are asked to explain the chart. Assume you have applied a full risk-based testing strategy.
Which of the following answers would you expect to best describe the pie chart? Number of correct responses: 1
Question 7
Multiple Choice
The following are the requirements identified as "critical": REQ-SEL-001. The user shall be able to combine all the three products with all the four durations to define an item to purchase REQ-SEL-002. The user shall be able to add a maximum of six different items to the shopping cart REQ-PUR-001. The user shall be able to purchase all the items in the shopping cart using a credit voucher REQ-PUR-002. The user shall be able to purchase all the items in the shopping cart using the available credit already charged on the smartcard REQ-PUR-003. The user shall be able to purchase all the items in the shopping cart using all the accepted credit cards (Visa, MasterCard and Great Wall Card) REG-LOGO-001. The user shall be able to logout (by clicking the logout button) from both the "select" and "purchase" pages going back to the "browse" page (anonymous navigation) Moreover the following quality risk item has been identified as "critical": QR-P1. The web customer portal might not be able to provide the expected response time (less than 10 sec) for the purchase transactions under a load of up-to 1000 concurrent users Test analysis for system testing has just begun and the following test conditions have been identified: TC-SEL-01. Test the combinations of products and durations to define an item to purchase TC-SEL-02. Test the maximum number of items, which can be added to the shopping cart TC-PUR-01. Test the purchase of an item TC-PUR-02. Test the purchase of an item with the credit charged on the smartcard Assume that you have used traceability to determine the logical test cases that cover all the requirements and the single risk item identified in that scenario. Which of the following is a positive logical test that is complete, is correct, and covers the REG-LOGO-001 requirement? Number of correct responses: 1
Question 8
Multiple Choice
The following are the exit criteria described in the test plan of a software product: EX1. The test suite for the product must ensure that at least each quality risk item is covered by at least one test case (a quality risk item can be covered by more test cases) . EX2. All test cases in the test suite must be run during the execution phase. EX3. Defects are classified into two categories: "C" (critical defect) and "NC" (non-critical defect) . No known C defects shall exist in the product at the end of the test execution phase. Which of the following information is useless when the specified exit criteria is evaluated? Number of correct responses: 1
Question 9
Multiple Choice
You are following a risk-based testing strategy. The test execution time is very limited. Assume that all the product risk items require more or less the same level of test effort.
Which of the following answers describes the best execution schedule in this scenario? Number of correct responses: 1
Question 10
Multiple Choice
You are the Test Manager of a new project that will have three formal levels of testing: unit, integration and system testing. The testing strategy you decide to adopt a blend of risk-based testing and reactive testing strategies. Which of the following answers describes the most consistent example of implementation of this test strategy during the execution of the system tests? Number of correct responses: 1
Question 11
Multiple Choice
Assume that no additional product risks have been identified during the first week of test execution.
Which of the following answers would you expect to best describe the residual risks associated with the identified product risks, at the end of the first week of test execution? Number of correct responses: 1
Question 12
Multiple Choice
You are the Test Manager of a project that adopts a V-model with four formal levels of testing: unit, integration, system and acceptance testing. On this project reviews have been conducted for each development phase prior to testing, which is to say that reviews of requirements, functional specification, high-level design, low-level design and code have been performed prior to testing. Assume that no requirements defects have been reported after the release of the product. Which TWO of the following metrics do you need in order to evaluate the requirements reviews in terms of phase containment effectiveness? Number of correct responses: 2
Question 13
Multiple Choice
The following chart plots the cumulative number of defects opened against the cumulative number of defects closed during system testing of a software product.
Which of the following statements is true? Number of correct responses: 1
Question 14
Multiple Choice
Which of the following statements represents the most effective contribution of the stakeholders to the completion of the failure mode analysis table? Number of correct responses: 1