Services
Discover
Homeschooling
Ask a Question
Log in
Sign up
Filters
Done
Question type:
Essay
Multiple Choice
Short Answer
True False
Matching
Topic
Certification
Study Set
Building Industry Consulting Service International (BICSI)
Exam 1: BICSI Registered Communications Distribution Designer - RCDD
Path 4
Access For Free
Share
All types
Filters
Study Flashcards
Practice Exam
Learn
Question 181
Multiple Choice
Exhibit: The diagram below is a typical configuration for:
Question 182
Multiple Choice
You have been asked to test and troubleshoot an installed base of cabling that is believed to be causing network problems. You are finding that there are high levels of return loss upon initial testing. What testing will best determine the reasons for these failures?
Question 183
Multiple Choice
When balanced twisted-pair copper cabling, return loss is a measurement of the:
Question 184
Multiple Choice
Select the appropriate task to complete section 2.2 of the work breakdown structure (WBS) below: 2 Technician 2.1 Install cabling 2.2 __________ 2.3 Activate wireless
Question 185
Multiple Choice
Select the appropriate task to complete the section 2.2 of the work breakdown structure below: 2. Technician 2.1 Install rack 2.2 _________ 2.3 Place fiber 2.4 Terminate fiber 2.5 Test fiber
Question 186
Multiple Choice
You are preparing to test newly installed open office cabling. Within the open office cabling, there are multiple consolidation points (CP) that were installed while waiting for furniture. How do you proceed with permanent link testing?
Question 187
Multiple Choice
What is the worst case acceptance value for attenuation when testing 2000 m (6562 ft) of 50/125 multimode fiber at a wavelength of 1300 nm when the fiber has 2 connector pairs and 3 splices?
Question 188
Multiple Choice
What is the PERT estimate of time for cable placement on a given job? - Optimistic time is 100 hours - Most likely time is 125 hours - Pessimistic time is 210 hours
Question 189
Multiple Choice
Which of the following does NOT describe one of the four main types of specifications?
Question 190
Multiple Choice
What type of estimate is based on the cost of performing similar work in the past, adjusted for current job conditions?
Question 191
Multiple Choice
Which is NOT true about conformance quality?
Question 192
Multiple Choice
At the end of the second week of a project, the earned value (EV) of work is $8000 USd and the planned value (PV) of work is $7000 USd. What is true about the project?
Question 193
Multiple Choice
Color codes for cross-connections fields have been used for many years. Which color is used to identify horizontal cable?
Question 194
Multiple Choice
All of the following are considered market or regional conditions that can impact construction costs EXCEPT:
Question 195
Multiple Choice
Where backbone cabling exceeds cabling lengths for the same performance or design (for product used in horizontal cabling) , there are three fundamental tests which should be considered when testing. They are:
Question 196
Multiple Choice
When developing a safety plan, consider all of the following EXCEPT:
Question 197
Multiple Choice
A work breakdown structure is:
Question 198
Multiple Choice
What is the PERT estimate (in hours) for project design where: - Optimistic time is 40 hours - Most likely time is 50 hours - Pessimistic time is 60 hours
Question 199
Multiple Choice
Premises optical fiber links should be tested:
Question 200
Multiple Choice
A scope of work should contain all of the following EXCEPT:
showing 181 - 200 of 340
Prev
Next
Prev
1
...
3
4
5
6
7
8
9
10
11
...
13
14
15
16
17
Next
Related Quizzes
Previous slide
Next slide
Access For Free