Solved

Use This Information to Answer the Following Questions

Question 4

Multiple Choice

Use this information to answer the following questions.
Consider the following Activity-On-Node (AON) PERT project.The three values that represent each activity's completion time (in days) correspond to an optimistic time,most likely time,and pessimistic time,respectively.
Use this information to answer the following questions. Consider the following Activity-On-Node (AON) PERT project.The three values that represent each activity's completion time (in days) correspond to an optimistic time,most likely time,and pessimistic time,respectively.    -Refer to the figure.What is the probability of not completing the project within 18 days? A) 0.0668 B) 0.4332 C) 0.9332 D) 0.4878 E) 0.0122
-Refer to the figure.What is the probability of not completing the project within 18 days?


A) 0.0668
B) 0.4332
C) 0.9332
D) 0.4878
E) 0.0122

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents