Use this information to answer the following questions.
Consider the following Activity-On-Node (AON) PERT project.The three values that represent each activity's completion time (in days) correspond to an optimistic time,most likely time,and pessimistic time,respectively.
-Refer to the figure.What is the probability of not completing the project within 18 days?
A) 0.0668
B) 0.4332
C) 0.9332
D) 0.4878
E) 0.0122
Correct Answer:
Verified
Q1: A graph that plots the total resources
Q2: Use this information to answer the following
Q3: Use this information to answer the following
Q5: Use this information to answer the following
Q6: Use this information to answer the following
Q7: Use this information to answer the following
Q8: Use this information to answer the following
Q9: Activity A has a standard cost of
Q10: Crash time is the longest time it
Q11: Use this information to answer the following
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents