Activity A has a standard cost of $500 and the standard time to complete Activity A is 5 weeks.The crash time for Activity A is 3 weeks and the crash cost is $600.What is the crash cost per week for Activity A?
A) $50
B) $100
C) $150
D) $200
E) $300
Correct Answer:
Verified