The design firm is required on the hospital project to define the sequence of tasks that must be started or finished exactly on time to meet the total schedule. What type of method of scheduling should they do to maintain this requirement?
A) Bar Chart
B) Milestone Chart
C) CPM Chart
D) Chart of Accounts
Correct Answer:
Verified