Two projects, A and B, are scored using three criteria that are weighted in the proportion 0.20, 0.30, and 0.50. Using a 5-point scale for each of the criteria, Project A is scored 5, 3, 2; Project B is scored 5, 2, 5. Circle all of the following that are true:
A) Project A has a weighted rating of 2.9
B) Project A has a weighted rating of 3.33
C) Project B has a weighted rating of 4.1
D) Project B has a weighted rating of 3.33
E) None of the above are correct
Correct Answer:
Verified
Q5: The purpose of contract negotiation is to
A)
Q6: The contract statement of work (CSOW) defines
A)
Q7: A complete RFP should include (circle all
Q8: A feasibility study
A) can be included in
Q9: In defining user needs, which of the
Q11: When planning a project, it is important
Q12: In which of the following kinds of
Q13: The purpose of contract negotiation is to
Q14: Signing of the contract ordinarily represents
A) approval
Q15: List in sequence the four phases of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents