Eight jobs have been sequenced at a single work center. Total processing time for the eight jobs is 34 hours and total flow time for the sequence is 85 hours. For this schedule, utilization is __________ and average jobs in the system is __________.
A) 100 percent; 10.625
B) low; .0941
C) 0.400 or 40 percent; 2.5
D) 0.235 or 23.5 percent; 4.25
E) maximized; minimized
Correct Answer:
Verified
Q63: Which of the following dispatching rules is
Q64: Average completion time for a schedule sequence
Q65: Five jobs are waiting for processing
Q66: Which of the following are limitations of
Q67: Five jobs are waiting to be
Q67: Sequencing (or dispatching):
A) assigns dates to specific
Q69: Which of the following is an advantage
Q70: Five jobs are waiting for processing
Q71: The priority rule that sequences jobs using
Q101: A recent advance in short-term scheduling that
Unlock this Answer For Free Now!