Five jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Sigma before work center Delta. According to Johnson's rule, what sequence of jobs will minimize the completion time for all jobs?
 Job  Sigma  Delta R4010S2530T5020U3535V5515\begin{array} { | c | c | c | } \hline \text { Job } & \text { Sigma } & \text { Delta } \\\hline R & 40 & 10 \\\hline \mathrm { S } & 25 & 30 \\\hline \mathrm { T } & 50 & 20 \\\hline \mathrm { U } & 35 & 35 \\\hline \mathrm { V } & 55 & 15 \\\hline\end{array}


A) R-S-T-U-V
B) S-V-T-R-U
C) S-U-T-V-R
D) V-R-U-S-T
E) none of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents