What is a schedule variance?


A) The budgeted cost of work performed during a specific time period (BCWP)
B) The budgeted cost of work scheduled during a specific time period (BCWS)
C) The difference between the budged cost of work performed and the budget cost of work scheduled for a specific time period (BCWP-BCWS)
D) The amount of time by which a project is behind schedule when no slack exists in the schedule budget
E) The difference between the money spent and the money projected to be spent on a project