In CCPM,a finite amount of time that can be added to a sequence of activities to non-critical tasks best describes
A) negative float.
B) safety float.
C) relaxed capacity.
D) feeding buffers.
Correct Answer:
Verified
Q62: Which of the following includes activities performed
Q63: Shortening an activity is called
A)float.
B)crash.
C)reduction.
D)smoothing.
Q64: The ratio of rise and run of
Q65: If the optimistic time is 3,the most
Q66: The completion time having the highest probability
Q68: An overall management philosophy introduced by Goldratt
Q69: What is PDM? Why is it useful?
Q70: The longest time that an activity might
Q71: Identify and describe three dependencies of project
Q72: Identify five benefits of networking project activities.