The addition of acceptance criteria factors to the milestone schedule in a project charter helps the team understand who will judge the quality of the deliverable associated with each milestone,and _____.
A) that stakeholder's role on the team.
B) the risk associated with each milestone.
C) the penalties for not achieving the desired quality.
D) what criteria will be used for that determination.
Correct Answer:
Verified
Q26: Which of these charter elements should persuade
Q27: Team operating principles are sometimes included in
Q28: Briefly discuss the importance of the project
Q29: On agile projects the first iteration is
Q30: During iteration planning in an agile project,agreement
Q32: Which of the following statements most accurately
Q33: What are risks,and why is it important
Q34: Which of the following statements accurately describes
Q35: The project charter serves all of the
Q36: A project sponsor is wise not to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents