Which of the Following Statements Most Accurately Identifies the Typical

Question 32

Multiple Choice

Which of the following statements most accurately identifies the typical contents of the project charter? 


A)  requirements, specifications, test protocols and test results 
B)  statement of work, terms and conditions, clauses and delivery instructions 
C)  business case, milestone schedule, resource estimates and team operating principles 
D)  purpose, literature review, methodology, results and conclusions

Correct Answer: