Which of the following charter elements defines the project purpose and justifies the necessity of the project?
A) scope control plan
B) acceptance criteria
C) business case
D) scope overview
Correct Answer:
Verified
Q29: On agile projects the first iteration is
Q30: During iteration planning in an agile project,agreement
Q31: The addition of acceptance criteria factors to
Q32: Which of the following statements most accurately
Q33: What are risks,and why is it important
Q34: Which of the following statements accurately describes
Q35: The project charter serves all of the
Q36: A project sponsor is wise not to
Q38: The milestone schedule in the project charter:
A) is
Q39: Within the project charter,the scope overview accomplishes
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents