Multiple Choice
Figure 7-3 System Integration Project
-Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,which activities can be delayed one day without impacting the expected project completion date?
A) Activity E - Install Software and Activity F - Test System
B) Activity C - Purchase Software and Activity E - Install Software
C) Activity C - Purchase Software and Activity D - Prepare Test Plan
D) none of these
Correct Answer:
Verified