Multiple Choice
Figure 8-4 Project Crashing Information
-Consider the project crashing information presented in Figure 8-4.Which activity should you crash to reduce this project by one day with the least incremental cost?
A) Activity A
B) Activity C
C) Activity E
D) Activity F
Correct Answer:
Verified