Question 1
True/False
Monitoring and controlling project work refers to the processes of tracking,reviewing and reporting progress to meet the performance objectives defined in the project plan.
Question 2
True/False
Some scope changes start as proposed changes to cost or schedule,just as some changes to cost or schedule start as proposed scope changes.
Question 3
True/False
When project managers authorize work,they should empower others to the extent possible,yet control them to the extent necessary.
Question 4
True/False
Control quality is the forward-looking process of using and improving the quality plan and policy to perform tasks that will most likely lead to creating project outputs to customers' satisfaction.
Question 5
True/False
The Schedule Performance Index (SPI)is a schedule performance measure expressed as the ratio of earned value (EV)to planned value (PV).
Question 6
True/False
On agile projects,because communication is frequent and rapid,a directional indicator showing that things are getting better or worse in some manner is more valuable than a more detailed and polished report.