Multiple Choice
This Agile project reporting tool is useful to Scrum Masters as it projects how close to plan the team is within a given time box,by providing a graphical representation of work effort remaining in an iteration versus the days left in an iteration.
A) Control chart
B) Burndown chart
C) Run chart
D) Progress report
Correct Answer: