After identifying the stakeholders,a _________should be created to maintain key information about them including contact information,their requirements and expectations,what stage in the project they have the most interest in,and so on.
A) stakeholder register
B) stakeholder plan
C) project plan
D) request for proposal
Correct Answer:
Verified
Q2: The need to manage interfaces and to
Q3: During project build-up,the project should move from
Q4: During project build-up,if the project is independent
Q5: _ is the process which begins when
Q6: _ problems are comparatively rare during project
Q7: During the main program phases of the
Q8: There are probably more opportunities for _
Q9: Personality conflicts during project phase-out are often
Q10: Before the goals of the shareholders can
Q11: The most common method of identifying stakeholders
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents