The use of __________ activity time estimates may reduce the chance that crashing the project will be needed.
A) one probabilistic
B) two probabilistic
C) three probabilistic
D) four probabilistic
Correct Answer:
Verified
Q8: _ describes the amounts of individual resources
Q9: _ times result from an attempt to
Q10: When crashing a project,our first task is
Q11: If the crash cost is $2,500,the normal
Q12: A project task is said to be
Q14: If the crash cost is $2,500,the normal
Q15: If deterministic time estimates are used,and if
Q16: In CPM,_ are specified.
A)exact levels of uncertainty
Q17: The points between the extreme points of
Q18: The standard practice with AOA and AON
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents