Billie Raney is in charge of a major construction project for her company. She has been informed that the plumbing installation has hit a snag and could be delayed. Billie is very concerned about this because she knows that any delay in the plumbing is likely to hold up the completion of the entire project. Which of the following does this suggests about the plumbing installation?
A) It is on the project's critical path.
B) It is an activity that has no immediate predecessors.
C) It is on the project's nodal network.
D) It is a part of the project's primary activity sequence.
Correct Answer:
Verified
Q103: Which of the following is true of
Q104: From the company's perspective, which of the
Q105: When the vice president of operations for
Q106: Given the nature of their products, many
Q107: What is the term for a firm's
Q109: Which of the following involves arranging for
Q110: In the terminology of the critical path
Q111: As a general location factor, which of
Q112: What is the best-known type of product
Q113: Paolo Brothers Inc. has been awarded a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents