Your next project consists of 5 consecutive 10-day activities,each estimated by a different worker in your organization.You have all secretly added your own safety margin of 4 days into your estimates and you watch in horror as the project manager whips out his copy of Critical Chain and slams it on the table midway through their first project meeting."I'm taking your buffers and making them my own," he bellows.You recoil from this news and do some quick mental arithmetic.Now that you know the project manager is a Goldratt disciple,you know that the new project buffer will be:
A) 25 days
B) 20 days
C) 15 days
D) 10 days
Correct Answer:
Verified
Q36: Which of these is a drawback for
Q37: Refactoring is the continuous process of streamlining
Q38: Wayne and Garth are engaged in XP
Q39: A product backlog is the final list
Q40: XYZ project organization has one workstation that
Q42: Which of the following statements about CCPM
Q43: What are the five steps behind the
Q44: What is the difference between the critical
Q45: Your boss catches you at the water
Q46: Alexander Demetrius Dickson,ADD to his friends,has three
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents