Which of these is a drawback for Agile Project Management?
A) Final outcomes are well-defined since Agile requirements are clearly articulated at the start of the design phase.
B) The users of the project deliverable tend to be uninformed as to project status until the delivery phase once the initial bid process has ended.
C) The project team will be unsure the deliverable works since testing is delayed to the very end of the project.
D) The frequent rescoping of a predictable project becomes wasted expense as it won't deliver added benefits.
Correct Answer:
Verified
Q31: Which of the following is NOT one
Q32: A project consists of four activities
Q33: The first step in TOC methodology is
Q34: Wayne and Garth are engaged in XP
Q35: Extreme programming advocates a large development staff,several
Q37: Refactoring is the continuous process of streamlining
Q38: Wayne and Garth are engaged in XP
Q39: A product backlog is the final list
Q40: XYZ project organization has one workstation that
Q41: Your next project consists of 5 consecutive
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents