Question 61
True/False
Gantt charts define dependency between project tasks before those tasks are scheduled.
Question 62
True/False
Project constraints are factors considered to be true,real,or certain without proof or demonstration.
Question 63
True/False
Responsibility matrix defines all project roles and indicates what responsibilities are associated with each role.
Question 64
True/False
A kill switch is a trigger that enables a project manager to close the project before completion.
Question 65
True/False
In the past,outsourcing was often used tactically,as a quick-fix,short-term solution to a particular need or problem which did not form part of an overall business strategy.
Question 66
True/False
A dependency is a logical relationship that exists between the project tasks,or between a project task and a milestone.
Question 67
True/False
The Project Management Office (PMO)is an internal department that oversees all organizational projects.
Question 68
True/False
The project requirements document defines the specifications for product/output of the project and is key for managing expectations,controlling scope,and completing other planning efforts.
Question 69
True/False
In-sourcing is an arrangement by which one organization provides a service or services for another organization that chooses not to perform them in-house.
Question 70
True/False
The project managers are individuals and organizations actively involved in the project or whose interests might be affected as a result of project execution or project completion.