The 100% Rule Suggests That Before a PERT Chart Is

Question 36

Multiple Choice

The 100% rule suggests that before a PERT chart is done,a project manager must:


A) Make sure 100% of the project is funded.
B) Make sure the project team is devoted solely or 100%, to this project.
C) Make sure that each person on the project team got 100% on their project management final exam.
D) Make sure 100% of the project tasks are defined.