The Critical Path in a PERT Chart Represents

Question 34

Multiple Choice

The critical path in a PERT chart represents:


A) The tasks that must be completed without errors.
B) The path of processes that is critical for system adoption.
C) The most important tasks of the whole project.
D) The longest path of tasks needed for project completion.

Correct Answer: