Within the project charter,the scope overview accomplishes all of the following EXCEPT:
A) identifies the major schedule milestones for the project
B) describes the work that must be performed to deliver a product,service or result.
C) distinguishes between what the project will and will not do.
D) describes at a high level what needs to be accomplished and how it will be done.
Correct Answer:
Verified
Q23: In the project charter,what types of resources
Q24: Which section of the project charter publicly
Q25: Project managers and teams should consider risks
Q27: The project charter serves all of the
Q29: On agile projects the first iteration is
Q30: During iteration planning in an agile project,agreement
Q31: Project charters typically include all of the
Q33: What are risks,and why is it important
Q34: The addition of acceptance criteria factors to
Q37: Which of the following charter elements defines
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents