Creating a realistic schedule is often an iterative process because several factors can limit how fast a project can be completed.All of the following factors can limit how fast a project can be scheduled and completed EXCEPT:
A) logical order
B) imposed dates
C) resource availability
D) quality metrics
Correct Answer:
Verified
Q6: The "start-to-start" logical relationship used in activity
Q13: In order for activities to be useful
Q20: If a project manager delays the start
Q21: All of the following strategies can help
Q21: Q25: All of the following problems contribute to Q26: The sequencing of activities is often based Q32: Which of the following responses identifies a Q33: Q35: Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents