All of the following strategies can help a project team to develop realistic time estimates for project activities EXCEPT:
A) adding a significant buffer to each activity
B) be sure to consider learning curves,interruptions and competing priorities
C) estimate times of completion without initial reference to a calendar
D) verify the time estimates with the people doing the work
Correct Answer:
Verified
Q6: The "start-to-start" logical relationship used in activity
Q13: In order for activities to be useful
Q17: Monte Carlo simulation is a process which
Q20: If a project manager delays the start
Q20: Even small delays on "near-critical" activities can
Q23: Creating a realistic schedule is often an
Q25: All of the following problems contribute to
Q26: The sequencing of activities is often based
Q32: Which of the following responses identifies a
Q35:
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents