Question 21
Multiple Choice
Figure 8-3 Programmers Resource Histogram -Consider the programmers resource histogram presented in Figure 8-3.If only six programmers are available to support this project,which of the following conclusions is valid?
Question 22
Multiple Choice
Figure 8-1 RACI Chart -Consider the RACI chart presented in Figure 8-1.What responsibility should the contract officer assume with respect to the statement of work?
Question 23
Multiple Choice
When estimating resource needs,project teams should consider all the following EXCEPT:
Question 24
Multiple Choice
Figure 8-3 Programmers Resource Histogram -Consider the programmers resource histogram presented in Figure 8-3.How many programmers are required during the fifth week of this project?
Question 25
Multiple Choice
Figure 8-4 Project Crashing Information -Consider the project crashing information presented in Figure 8-4.What is the cost to complete this project in the normal time?
Question 26
Multiple Choice
Project managers must often face the challenge of compressing the project schedule.All of the following actions can be taken to reduce the duration of the critical path EXCEPT:
Question 27
Multiple Choice
Project managers often confront the challenge of reducing excessive time commitments and overloads among project resources.All of the following methods represent a potentially viable strategy to reduce work overloads EXCEPT: