Question 41
Short Answer
The customer's prioritized list of key features desired when the project is completed is the ____________ backlog.
Question 42
Short Answer
Short time frames (time boxes)that typically last from one to four weeks are called __________.
Question 43
Short Answer
Scrum uses a series of coordinated _________ to manage the development process.
Question 44
Short Answer
Using Scrum methodology, specific features are created according to four distinct phases during each sprint.The third phase is to ________ the feature so that it is functional.
Question 45
Short Answer
The development team is a key role when considering the Scrum process.The team is _____________ in the sense that they decide among themselves who should do what and what should be done.
Question 46
Short Answer
A(n)_________ is a person who acts on behalf of customers/end users to represent their interests.
Question 47
Short Answer
The ____________ facilitates the Scrum process and resolves impediments at the team and organizational level.
Question 48
Short Answer
When teams reflect, learn, and adapt to change, when their work updates the plan, they are following the agile project management principle of _________________.
Question 49
Short Answer
In response to the financial concerns associated with agile project management, many organizations establish ____________, which is the maximum budget that should not be exceeded in the development of a given product or service.
Question 50
Short Answer
Using Scrum methodology, specific features are created according to four distinct phases during each sprint.The first phase is _________ and review of functional requirements that will be needed to complete the feature.
Question 51
Short Answer
Using Scrum methodology, a(n)____________ is typically made up of five to nine people with cross-functional skill sets.
Question 52
Short Answer
Project ___________ varies according to the extent the project scope is known and stable and the technology to be used is known and proven.
Question 53
Short Answer
A(n)_________ is defined as a piece of a product that delivers some useful functionality to a customer.
Question 54
Short Answer
A new holistic approach in new commercial product development efforts where the cross-functional team collaborating to develop a new product is compared to rugby, where the whole team tries to go the distance as a unit, is known as _________.
Question 55
Short Answer
Using Scrum methodology, specific features are created according to four distinct phases during each sprint.The second phase is the development of a __________ that meets the requirements of the feature.