Question 21
Multiple Choice
A _________ activity is one that has more than one activity taking place at the same time.
Question 22
Multiple Choice
When creating a project network, your primary input will be the
Question 23
Multiple Choice
A project network provides the basis for ________________________________ .
Question 24
Multiple Choice
A _________ activity is one that has more than one activity immediately preceding it.
Question 25
Multiple Choice
Which of the following is true about hammock activities?
Question 26
Multiple Choice
System documentation cannot end until three days after testing has started.This is an example of which kind of lag?
Question 27
Multiple Choice
Tom is responsible for ordering hardware for a custom home his company is building.The contractor installing the hardware is scheduled to start in 5 working days, but the hardware is on backorder and will not arrive for another 9 working days.Fortunately, Tom has 10 days of slack; however, he shares this slack with the hardware installer.He will have to let the contactor know that the hardware will be ready 4 days later than expected and that the slack for the installer has been reduced by 4 days.Tom and the installer share 10 days of
Question 28
Multiple Choice
The likelihood the original critical path(s) will change once the project is initiated is referred to as
Question 29
Multiple Choice
When completing a backward pass, you carry the LS to the next preceding activity to establish the LF, unless the next preceding activity is a burst activity, in which case you select
Question 30
Multiple Choice
If testing cannot be completed any earlier than four days after the prototype has been built, what type of lag exists?
Question 31
Multiple Choice
A _________ activity is one that has more than one activity immediately following it.
Question 32
Multiple Choice
If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?
Question 33
Multiple Choice
The minimum amount of time a dependent activity must be delayed to begin or end is referred to as
Question 34
Multiple Choice
Which of the following will correctly calculate the total slack in an activity?
Question 35
Multiple Choice
The assumption that all immediate preceding activities must be 100% complete is too restrictive in some situations.When an activity is broken down into smaller segments in order to start the succeeding activity sooner, this is called
Question 36
Multiple Choice
If a project has more than one activity that can begin when the project is to start, a common start node should be used to indicate a clear project beginning on the network.Without a common start node, each path is a