Question 61
True/False
In developing a project network, neither looping nor conditional statements are permitted.
Question 62
True/False
Burst activities have more than one activity immediately following them (more than one dependency arrow flowing from them).
Question 63
True/False
An activity can include only one work package.
Question 64
True/False
An activity is an element of the project that always requires time.
Question 65
Short Answer
A(n)__________ activity is frequently used to identify the use of fixed resources or costs over a segment of the project.
Question 66
Short Answer
When an activity with a long duration is broken into smaller segments so that the following activities can begin sooner it is called __________.
Question 67
True/False
A merge activity is one that merges with other activities into a succeeding activity.
Question 68
True/False
An activity cannot begin until ALL preceding connected activities have been completed.
Question 69
Short Answer
A network has only one critical path and the slack for noncritical activities is high.This network would appear to have a _______ level of sensitivity.
Question 70
Short Answer
________ can never be negative and applies only to the last activity in a single chain of activities.
Question 71
True/False
It is acceptable for arrows to cross one another in a network diagram.
Question 72
Short Answer
The _________ lag is the most typical type of lag that is encountered in developing networks.
Question 73
Short Answer
The longest path through a project network is called the _________.
Question 74
Short Answer
___________ reflects the likelihood the original critical path(s)will change once the project is initiated.
Question 75
Short Answer
A(n)________ is the minimum amount of time a dependent activity must be delayed to begin or end.
Question 76
True/False
Experience suggests that when there are multiple starts, a common start node should be used to indicate a clear project beginning on the network.Similarly, a single project end node can be used to indicate a clear ending.