True/False
Using the random order or "whim" priority rule to sequence production jobs means that supervisors select whichever job they feel like running first.
Question 2
True/False
A system that "backward schedules" is designed to determine and report the earliest date an order can be completed.
Question 3
True/False
In infinite loading no consideration is given directly to whether there is sufficient capacity at the resources required to complete the work,nor is the actual sequence of the work as done by each resource in the work center considered.
Question 4
True/False
The FCFS priority rule used in sequencing production jobs will always result in a better solution than the LCFS rule.
Question 5
True/False
In production scheduling the process of determining which job to start first on some machine or in some work center is known as sequencing or priority sequencing.
Question 6
True/False
Shop-floor control (or production activity control)can involve expediting late and critical orders.
Question 7
True/False
Initiating performance of scheduled work is commonly termed "dispatching" of orders.
Question 8
True/False
Shop-floor control (or production activity control)can involve reviewing the status and controlling the progress of orders as they are being worked on.
Question 9
True/False
A shop-floor control system is a system that uses data from the shop floor as well as data processing files to maintain and communicate status information on shop orders and work centers.
Question 10
True/False
Theoretically,all schedules are feasible when finite loading is used.
Question 11
True/False
The textbook underscores the importance of scheduling with the phrase "workflow equals cash flow and scheduling lies at the heart of the process".
Question 12
True/False
The assignment method of job sequencing is a special case of the transportation method of linear programming.
Question 13
True/False
In finite loading no consideration is given directly to whether there is sufficient capacity at the resources required to complete the work,nor is the actual sequence of the work as done by each resource in the work center considered.