The following information relates to Ramesy Manufacturing:
To produce a unit of product
There is a wait time of 5 minutes before the Cutting Department begins a batch, 15 minutes between the Cutting and Welding departments, a move and pre-wait between Welding and Polishing of 12 minutes, and a move and pre-wait between the Polishing and Finishing departments of 8 minutes.
-Refer to the figure.If Ramesy produces in batches of 10 units,how much time would have elapsed by the time the 10th unit is produced under a manufacturing cell environment (assuming the cell is processing continuously) ?
A) 60 minutes
B) 65 minutes
C) 150 minutes
D) 125 minutes
Correct Answer:
Verified
Q32: Which of the following is considered a
Q33: Why is units shipped instead of units
Q34: How is overproduction of good controlled in
Q35: Why might labour costs be reduced in
Q36: How is production triggered in a demand-pull
Q38: Which of the following is characteristic of
Q39: Which of the following is an advantage
Q40: The following information relates to Ramesy
Q41: Q42:
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents