Use the Information Below to Answer the Following Questions:
on

Question 40

Multiple Choice

Use the information below to answer the following questions:
On 1 January 2010, Romulus Ltd signed a contract worth $21 000 000 to construct a light rail from here to there. The light rail was to be built over 3 years, with progress payments of $7 000 000 to be made at the end of each year. Estimated costs were $15 000 000 and the following costs incurred and paid by Romulus Ltd were in accordance with estimates and represented the percentage completed in each year:
2010 $8000000 2011 $5000000 2012$2000000  \begin{array}{llcc} & \text {\$ } \\ \text {2010 } &\$ 8000000 \\ \text { 2011 } &\$ 5000000 \\ \text { 2012} &\$ 2000000 \\ \text { } &\\ \text { } &\\\end{array}

The project was completed in December 2012.
-Using the completion of production method,what profit would Romulus Ltd report in 2012?


A) $800 000
B) $5 000 000
C) $6 000 000
D) $0.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents