Solved

Use the Information Below to Answer the Following Questions:
on

Question 38

Multiple Choice

Use the information below to answer the following questions:
On 1 January 2010, Peter Ltd signed a contract worth $64 000 000 to construct the Cycling Stadium. The stadium was to be built over three years, with progress payments as follows:
$ 31 December 2010 $15000000 31 December 2011 $20000000 31 December 2012 $29000000\begin{array} { r r } & \$ \\\text { 31 December 2010 } & \$ 15000000 \\\text { 31 December 2011 } & \$ 20000000 \\\text { 31 December 2012 } & \$ 29000000\end{array}
Estimated costs were $50 000 000. The project was 35% complete at the end of 2010, 75% complete at the end of 2011, and 100% complete at the end of 2012. Revenues and costs were as estimated.
-What profit was earned during 2012 if the percentage of completion method was used?


A) $3 500 000
B) $5 600 000
C) $6 343 750
D) $14 000 000.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents