Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity) .Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project?
A) 34
B) 38
C) 42
D) 48
Correct Answer:
Verified
Q7: Concurrent activities are:
A)Activities that must be done
Q16: Activities C,D,and E in the project represented
Q20: Q20: An activity has an expected duration and Q22: An activity has an optimistic time estimate Q24: The variance of an activity is given Q25: Project Test Bank is composed of Q32: An activity has an optimistic time estimate Q35: What are hammock activities and when should Q39: A merge activity has two or more
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents