Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity) .Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project?
A) 34
B) 38
C) 42
D) 48
Correct Answer:
Verified
Q20: Q21: Preceding activities are those that must occur Q22: Project Test Bank is composed of Q22: An activity has an optimistic time estimate Q24: The variance of an activity is given Q26: At a merge point in a forward Q32: An activity has an optimistic time estimate Q34: An activity has an optimistic time estimate Q35: What are hammock activities and when should Q39: A merge activity has two or more
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents