Multiple Choice
A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities B,C,and D can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity?
A) 11, 30
B) 7, 24
C) 11, 24
D) 7, 36
Correct Answer: