A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities H and I can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity?
A) 13, 36
B) 13, 24
C) 24, 36
D) 7, 36
Correct Answer:
Verified
Q66: Q69: A project has the precedence requirements Q73: Use the information in the table Q75: A gentleman farmer maniacally works on Q75: The least amount of float is found: Q76: Use the information in the table to Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents
A)In