What is the slack time for Activity D given the activity times and precedence requirements shown in the table?
A) 2
B) 1
C) 0
D) 3
Correct Answer:
Verified
Q73: Use the information in the table
Q74: A project has the precedence requirements
Q75: The least amount of float is found: