Question 81
True/False
In critical path scheduling,slack is computed as the difference between finish and start times.
Question 82
True/False
An activity in a network diagram has an optimistic time estimate of five days,a most likely time estimate of seven days,and a pessimistic time estimate of 15 days.Its expected time is eight days.
Question 83
True/False
Removing safety time from the individual activities and putting the total safety time at the end of the critical path creates a project buffer.
Question 84
True/False
Accounting uses project management information to provide a time line for the marketing program.
Question 85
True/False
With probabilistic time estimates for activities,(m)denotes the mean time.
Question 86
True/False
Crashing is shortening the total time for completing a project by incurring higher costs from shortening activities.
Question 87
True/False
For projects whose activities have probabilistic time estimates,the probability of completing the project in a specified amount of time is determined by the standard deviation for the critical path only.
Question 88
Essay
List and briefly describe the phases in the project life cycle.
Question 89
True/False
When we are unsure about the duration of project activities,we use probabilistic time estimates.
Question 90
True/False
A Gantt chart can be use to display graphically the scheduled times for activities.
Question 91
True/False
In network diagramming,arrows represent precedence relationships.
Question 92
True/False
The sum of the activity times on the critical path determines the total slack available.
Question 93
Essay
What are the steps involved in using network planning techniques?
Question 94
True/False
In making a forward pass through a network,three activities are immediate predecessors for activity T.The early start time for activity T is the largest EF for the three activities that are immediate predecessors for activity T.