Solved

The Critical Path in a PERT Chart Represents the ______

Question 144

Multiple Choice

The critical path in a PERT chart represents the ______.


A) areas of operations that require the least amount of technical support
B) areas of operations that have abundant and extra time
C) sequence of operations that involves outside suppliers
D) sequence of operations that requires the longest time for completion

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents