As part of a time study a particular job was analyzed. The study included 20 job cycles and the following cumulative times and performance rating factors for each element were reported: Assuming an allowance factor of 20% the standard time for this job would be
A) 10.08 minutes.
B) 12.10 minutes.
C) 14.73 minutes.
D) 16.58 minutes.
Correct Answer:
Verified
Q13: How many cycles should be used in
Q18: As part of its quality-improvement program a
Q20: As part of a time study a
Q20: The basic principle underlying an incentive piece-rate
Q21: How many observations should be taken to
Q22: A work sampling study is being conducted
Q24: How many observations should be taken to
Q25: Management believes a critical piece of equipment
Q25: For a particular time study a company
Q26: For a particular time study a company
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents