Question 121
Multiple Choice
Easy Tax is a service company that prepares tax returns. An outside auditor has examined 20 samples each containing one completed tax return. Consider a service process that completes tax returns. An auditor has taken 20 samples of samples containing one completed tax return. The total number of defects observed over the 20 samples is 200. The LCL for the control chart constructed using three sigma is
Question 122
Multiple Choice
Marble Inc. makes countertops from a variety of high-end materials. To monitor the quality of its production processes the company randomly selects one countertop and counts the number of blemishes. The results for ten samples are shown below:
Given the sample information above, the LCL using sigma = 3 for this process would be
Question 123
Multiple Choice
Consider aEasy Tax is a service processcompany that completesprepares tax returns. An outside auditor has takenexamined 20 samples each containing one completed tax return. The total number of defects observed over the 20 samples is 200. The centerline for the control chart constructed is
Question 124
Multiple Choice
Marble Inc. makes countertops from a variety of high-end materials. To monitor the quality of its production processes the company randomly selects one countertop and counts the number of blemishes. The results for ten samples are shown below: 5.
6. Given the sample information above, the UCL using sigma = 3 for this process would be
Question 125
Multiple Choice
Consider a production process for a 5.0 oz. energy drink. A quality engineer has taken 15 samples each containing 6 energy drinks. The sum of the ranges of the energy drinks in the 15 samples is 12.68. The sum of the average of the energy drinks in the 15 samples is 80.20. The centerline for the control chart reporting variability between the sample means is
Question 126
Multiple Choice
5390. Pizazz manufactures a 5.0 oz. energy drink of the same name. Because the cans are so small, consumers are concerned that they are not receiving the full 5 ounces in each can. A quality engineer at the company is charged with analyzing the filling process and ensuring accurate readings. On 15 different occasions over the past month, she has taken a sample of 6energy drinks off the production line and recorded their weight. If the sum of the sample means is 80.20 ounces and the sum of the sample ranges is 12.68 ounces, the UCL for an X-bar chart of this process would beConsider a production process for a 5.0 oz. energy drink. A quality engineer has taken 15 samples each containing 6 energy drinks. The sum of the average of the energy drinks in the 15 samples is 80.20. The sum of the ranges of the energy drinks in the 15 samples is 12.68. The UCL for the control chart reporting variability between the sample means is
Question 127
Multiple Choice
Consider a production process for a 5.0 oz. energy drink. A quality engineer has taken 15 samples each containing 6 energy drinks. The sum of the ranges of the energy drinks in the 15 samples is 12.68. The UCL for the control chart reporting variability within the samples is
Question 128
Multiple Choice
Consider a production process that produces tires. A quality engineer has taken 15 samples, each containing 200 tires. The total number of defective tires over the 15 samples is 340. The LCL for the control chat constructed using two sigma is
Question 129
Short Answer
Pizazz manufactures a 5.0 oz. energy drink of the same name. Because the cans are so small, consumers are concerned that they are not receiving the full 5 ounces in each can. A quality engineer at the company is charged with analyzing the filling process and ensuring accurate readings. On 15 different occasions over the past month, she has taken a sample of 6 energy drinks off the production line and recorded their weight. If the sum of the sample means is 80.20 ounces and the sum of the sample ranges is 12.68 ounces, the UCL for an R-chart of this process would be
Question 130
Short Answer
Pizazz manufactures a 5.0 oz. energy drink of the same name. Because the cans are so small, consumers are concerned that they are not receiving the full 5 ounces in each can. A quality engineer at the company is charged with analyzing the filling process and ensuring accurate readings. On 15 different occasions over the past month, she has taken a sample of 6 energy drinks off the production line and recorded their weight. If the sum of the sample means is 80.20 ounces and the sum of the sample ranges is 12.68 ounces, the centerline for an X-bar chart of this process would be
Question 131
Multiple Choice
Marble Inc. makes countertops from a variety of high-end materials. To monitor the quality of its production processes the company randomly selects one countertop and counts the number of blemishes. The results for ten samples are shown below:
Given the sample information above, the average number of defects per unit for this process would be
Question 132
Multiple Choice
Consider a service process that completes tax returns. An auditor has taken 20 samples each containing one completed tax return. Easy Tax is a service company that prepares tax returns. An outside auditor has examined 20 samples each containing one completed tax return. The total number of defects observed over the 20 samples is 200. The standard deviation for the control chart is
Question 133
Multiple Choice
Easy Tax is a service company that prepares tax returns. An outside auditor has examined 20 samples each containing one completed tax return. Consider a service process that completes tax returns. An auditor has taken 20 samples each containing one completed tax return. The total number of defects observed over the 20 samples is 200. The UCL for the control chart constructed using three sigma is
Question 134
Multiple Choice
Consider a production process for a 5.0 oz. energy drink. A quality engineer has taken 15 samples each containing 6 energy drinks. The sum of the ranges of the energy drinks in the 15 samples is 12.68. The LCL for the control chart reporting variability within the samples is
Question 135
Multiple Choice
Consider a production process that produces tires. A quality engineer has taken 15 samples, each containing 200 tires. The total number of defective tires over the 15 samples is 340. The sample standard deviation is