Solved

Which of the Following Statements Is Incorrect About the PERT

Question 3

Multiple Choice

Which of the following statements is incorrect about the PERT method of project scheduling?


A) PERT requires three time estimates for scheduling a given activity.
B) PERT assumes that the actual activity times are distributed according to the beta probability distribution.
C) PERT assumes that the statistical variation in total project completion times can be computed by multiplying variances along the critical path.
D) None of the above

Correct Answer:

verifed

Verified

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents