Which of the following statements is incorrect about the PERT method of project scheduling?
A) PERT requires three time estimates for scheduling a given activity.
B) PERT assumes that the actual activity times are distributed according to the beta probability distribution.
C) PERT assumes that the statistical variation in total project completion times can be computed by multiplying variances along the critical path.
D) None of the above
Correct Answer:
Verified
Q1: Estimating the time required for each task
Q4: The advantage(s)of the network method over the
Q5: CPM network scheduling assumes a second order
Q6: Which of the following statements about CPM
Q7: A network-based project scheduling method that requires
Q8: The project management concept that can be
Q9: Multiple critical paths can exist under CPM
Q10: Controlling a project does NOT entail:
A)Monitoring costs,time,and
Q11: Project management requires:
A)Scheduling,planning,and controlling
B)Quantitative skills
C)Behavioral skills
D)All of
Q11: "Slack" refers to the difference between:
A)Late and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents